How to Level Resources Across Projects in Microsoft Project Online

Aamir Naveed AkramAamir Naveed Akram Nov 22, 2026 868 views

Question details

The user wants to understand how to level shared resources across active Project Online projects without leveling the entire portfolio daily.

How to Level Resources Across Projects in Microsoft Project Online
Product
Microsoft Project Online and Project Professional
Device & OS
not provided
Scenario
Approximately ten projects are planned, but only three are executed at the same time and may compete for enterprise resources.
Observed behavior
The goal is to resolve resource overallocation among active projects using project and task priorities while keeping the leveling process manageable.
Before you start

Connect Project Professional to the Project Online environment and identify the active projects that share enterprise resources. Review their saved and published assignments, resource availability, and project priorities before leveling.

Solution 1Recommended

Level Shared Resources Across the Active Projects

Use Project Professional to resolve conflicts among the projects currently being executed instead of leveling the whole portfolio.

Project priority helps determine which project receives preference when shared resources are overallocated across projects. Task priority helps determine which tasks receive preference when conflicts occur within a project.

Resource Center displays enterprise resources and their availability; it does not independently reserve a resource just because the resource is listed there. Review assignments and booking details to understand existing commitments.

1
Open the active projects

In Project Professional, connect to Project Online and use File > Open to open the active projects that share resources. Create a master project and insert those projects as subprojects so you can review them together.

2
Review project and task priorities

In each project, open Project > Project Information to review its Priority value. To review an individual task's priority, open Task Information for that task.

3
Set the leveling order

In the master project, open Resource > Leveling Options and select Priority, Standard under Leveling order. Review the remaining settings, including whether leveling can adjust individual assignments.

4
Level and review the schedule

Choose Resource > Level All, then inspect the affected tasks and dates in the Gantt Chart and Resource Usage views. Check for delays or remaining overallocation before accepting the result.

5
Save and publish changes

Save the affected projects and use File > Publish for each project whose updated schedule needs to be shared. Recheck and relevel weekly or biweekly, or sooner if assignments or schedules change significantly.

Level Shared Resources Across the Active Projects
Check commitments outside the active set: Limiting leveling to the open projects reduces the work involved, but do not assume it resolves every portfolio conflict. Review other projects' published assignments and resource availability in Resource Center, especially when planned projects also use the same resources.
Free Microsoft Office alternative

Track Project Resource Plans in WPS Office

WPS Office is a free, lightweight alternative for working with familiar Office documents and spreadsheets. Use its familiar interface to maintain resource-planning worksheets and move compatible Office files into your workflow. It does not replace Project Online resource leveling.

Create resource allocation and project tracking worksheets in WPS SpreadsheetsWork with Microsoft Excel XLSX files and other common Office formatsUse a familiar interface to transition compatible documents and spreadsheetsKeep everyday document and spreadsheet work in one lightweight suite
microsoft office alternative - wps office

Frequently Asked Questions

Where do I set the leveling order in Project Professional?

Open Resource > Leveling Options and choose Priority, Standard under Leveling order. Review the other options before running Resource > Level All.

Can I level only the three projects currently being executed?

Yes. Open the active projects that share resources and level them together in a master project. Also review other published assignments in Resource Center so you do not overlook commitments outside that set.

Does adding a resource to Resource Center reserve its time?

No. Resource Center lists enterprise resources and helps you review availability. Check project assignments and booking details to determine how their time is committed.

How often should I relevel the active projects?

A weekly or biweekly review can be a starting point. Recheck sooner when assignments, availability, or project schedules change significantly, then use Resource > Level All if leveling is needed.

Should I publish projects after leveling?

If the updated schedules need to be shared through Project Online, save each affected project and use File > Publish. Review the resulting dates and assignments before publishing.