How to Level Resources Across Projects in Microsoft Project Online
Question details
The user wants to understand how to level shared resources across active Project Online projects without leveling the entire portfolio daily.

- Product
- Microsoft Project Online and Project Professional
- Device & OS
- not provided
- Scenario
- Approximately ten projects are planned, but only three are executed at the same time and may compete for enterprise resources.
- Observed behavior
- The goal is to resolve resource overallocation among active projects using project and task priorities while keeping the leveling process manageable.
Connect Project Professional to the Project Online environment and identify the active projects that share enterprise resources. Review their saved and published assignments, resource availability, and project priorities before leveling.
Level Shared Resources Across the Active Projects
Use Project Professional to resolve conflicts among the projects currently being executed instead of leveling the whole portfolio.
Project priority helps determine which project receives preference when shared resources are overallocated across projects. Task priority helps determine which tasks receive preference when conflicts occur within a project.
Resource Center displays enterprise resources and their availability; it does not independently reserve a resource just because the resource is listed there. Review assignments and booking details to understand existing commitments.
In Project Professional, connect to Project Online and use File > Open to open the active projects that share resources. Create a master project and insert those projects as subprojects so you can review them together.
In each project, open Project > Project Information to review its Priority value. To review an individual task's priority, open Task Information for that task.
In the master project, open Resource > Leveling Options and select Priority, Standard under Leveling order. Review the remaining settings, including whether leveling can adjust individual assignments.
Choose Resource > Level All, then inspect the affected tasks and dates in the Gantt Chart and Resource Usage views. Check for delays or remaining overallocation before accepting the result.
Save the affected projects and use File > Publish for each project whose updated schedule needs to be shared. Recheck and relevel weekly or biweekly, or sooner if assignments or schedules change significantly.

Track Project Resource Plans in WPS Office
WPS Office is a free, lightweight alternative for working with familiar Office documents and spreadsheets. Use its familiar interface to maintain resource-planning worksheets and move compatible Office files into your workflow. It does not replace Project Online resource leveling.

Frequently Asked Questions
Where do I set the leveling order in Project Professional?
Open Resource > Leveling Options and choose Priority, Standard under Leveling order. Review the other options before running Resource > Level All.
Can I level only the three projects currently being executed?
Yes. Open the active projects that share resources and level them together in a master project. Also review other published assignments in Resource Center so you do not overlook commitments outside that set.
Does adding a resource to Resource Center reserve its time?
No. Resource Center lists enterprise resources and helps you review availability. Check project assignments and booking details to determine how their time is committed.
How often should I relevel the active projects?
A weekly or biweekly review can be a starting point. Recheck sooner when assignments, availability, or project schedules change significantly, then use Resource > Level All if leveling is needed.
Should I publish projects after leveling?
If the updated schedules need to be shared through Project Online, save each affected project and use File > Publish. Review the resulting dates and assignments before publishing.