Why Microsoft Project Time-Phased Actual Costs Change

Aamir Naveed AkramAamir Naveed Akram Nov 25, 2026 868 views

Question details

Determine why prior months' time-phased actual costs change after a Microsoft Project file is reopened.

Why Time-Phased Actual Costs Change in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A project uses a cost resource assigned to an activity, and the user needs reliable monthly actual costs for variance reporting.
Observed behavior
Time-phased actual costs from previous months change even though the user has not modified the task properties.
Before you start

Identify the affected task, cost resource, and months, and note the actual cost values before and after reopening the file. Record the Project version, build, and installation type so you can check the applicable updates.

Solution 1Recommended

Inspect the Cost Resource Assignment and Calculation Settings

Use this approach to identify whether assignment data or Project settings are affecting the reported actual costs.

A change in time-phased values does not by itself identify the cause. Compare the assignment details and calculation settings before and after reopening or recalculating the project.

1
Show time-phased actual costs

Open the project and select View > Task Usage. Right-click the time-phased grid and select Actual Cost, then locate the affected task and its cost resource assignment.

2
Compare the assignment

Expand the task in Task Usage and compare the resource assignment's actual costs for the affected months with the values you recorded. Inspect the assignment and task dates for changes.

3
Check calculation options

Open File > Options > Schedule and review the calculation options, including whether actual costs are calculated by Project and whether updating task status updates resource status. Note the current settings before changing anything.

4
Check the status date

Open Project > Status Date and note the date used for reporting. Compare the time-phased actual costs after any relevant status update or recalculation.

5
Validate the baseline

Use View > Tables > Variance or a cost table to compare actuals with the approved baseline. Check the baseline before using Project > Set Baseline, since setting it again can overwrite existing baseline data.

Inspect the Cost Resource Assignment and Calculation Settings
Avoid changing settings without testing: Test any setting change on a separate copy and compare the affected months again. The appropriate settings depend on how your organization enters and reports actual costs.
Free Microsoft Office alternative

Use WPS Spreadsheets for Cost Variance Reports

WPS Office is a free, lightweight, easy-to-use Office alternative with a familiar interface and Microsoft Office format compatibility for smoother migration. Use WPS Spreadsheets to review and report exported cost data; it does not fix Microsoft Project calculation issues.

Review exported monthly costs and variances in spreadsheetsOpen and edit Microsoft Excel XLSX filesWork with Word DOCX and PowerPoint PPTX filesUse a familiar interface for everyday Office tasks
microsoft office alternative - wps office

Frequently Asked Questions

Where can I see actual costs by month in Microsoft Project?

Open View > Task Usage, right-click the time-phased grid, and select Actual Cost. Adjust the timescale to show months and expand the task to inspect its resource assignments.

Can a cost resource assignment affect time-phased actual costs?

The assignment is where the cost resource's values are associated with the task. Inspect it in Task Usage and compare its time-phased actual costs and dates before and after reopening the project.

Will the July 2016 update include all previous Project updates?

Not necessarily for every installation. Check the update's Microsoft documentation for its prerequisites, supersedence, and whether it applies to your Click-to-Run or MSI installation.

How do I protect the approved baseline for variance reporting?

Review the existing baseline before using Project > Set Baseline. Setting a baseline again can overwrite the selected baseline, so follow your organization's approval process before doing so.