Why Microsoft Project Time-Phased Actual Costs Change
Question details
Determine why prior months' time-phased actual costs change after a Microsoft Project file is reopened.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project uses a cost resource assigned to an activity, and the user needs reliable monthly actual costs for variance reporting.
- Observed behavior
- Time-phased actual costs from previous months change even though the user has not modified the task properties.
Identify the affected task, cost resource, and months, and note the actual cost values before and after reopening the file. Record the Project version, build, and installation type so you can check the applicable updates.
Inspect the Cost Resource Assignment and Calculation Settings
Use this approach to identify whether assignment data or Project settings are affecting the reported actual costs.
A change in time-phased values does not by itself identify the cause. Compare the assignment details and calculation settings before and after reopening or recalculating the project.
Open the project and select View > Task Usage. Right-click the time-phased grid and select Actual Cost, then locate the affected task and its cost resource assignment.
Expand the task in Task Usage and compare the resource assignment's actual costs for the affected months with the values you recorded. Inspect the assignment and task dates for changes.
Open File > Options > Schedule and review the calculation options, including whether actual costs are calculated by Project and whether updating task status updates resource status. Note the current settings before changing anything.
Open Project > Status Date and note the date used for reporting. Compare the time-phased actual costs after any relevant status update or recalculation.
Use View > Tables > Variance or a cost table to compare actuals with the approved baseline. Check the baseline before using Project > Set Baseline, since setting it again can overwrite existing baseline data.

Check the Microsoft Project Build and Applicable Updates
Use this approach to determine whether an update applies to the installed Project version and deployment type.
Use WPS Spreadsheets for Cost Variance Reports
WPS Office is a free, lightweight, easy-to-use Office alternative with a familiar interface and Microsoft Office format compatibility for smoother migration. Use WPS Spreadsheets to review and report exported cost data; it does not fix Microsoft Project calculation issues.

Frequently Asked Questions
Where can I see actual costs by month in Microsoft Project?
Open View > Task Usage, right-click the time-phased grid, and select Actual Cost. Adjust the timescale to show months and expand the task to inspect its resource assignments.
Can a cost resource assignment affect time-phased actual costs?
The assignment is where the cost resource's values are associated with the task. Inspect it in Task Usage and compare its time-phased actual costs and dates before and after reopening the project.
Will the July 2016 update include all previous Project updates?
Not necessarily for every installation. Check the update's Microsoft documentation for its prerequisites, supersedence, and whether it applies to your Click-to-Run or MSI installation.
How do I protect the approved baseline for variance reporting?
Review the existing baseline before using Project > Set Baseline. Setting a baseline again can overwrite the selected baseline, so follow your organization's approval process before doing so.