Calculate Working Days Until or After a Project Deadline in Excel
Question details
The user needs an Excel formula to calculate the exact number of working days remaining until a deadline (as a negative number) or the number of days a project is overdue (as a positive number), specifically excluding weekends and designated holidays.
- Product
- Excel
- Device & OS
- not provided
- Scenario
- Tracking project timelines and computing accurate days remaining or overdue for active tasks.
- Observed behavior
- The standard date calculations might result in an off-by-one error because the default function includes both the start and end dates in its total count.
Ensure you have a designated column or range in your spreadsheet that lists all custom holidays, as standard functions only exclude default weekend days.
Use the NETWORKDAYS Function with an Adjustment
Utilize the NETWORKDAYS function to find the difference between the deadline and the current date, subtracting 1 to adjust for the inclusive date calculation.
The NETWORKDAYS function is designed to return the number of whole working days between a start date and an end date. It automatically excludes Saturdays and Sundays, and can exclude custom holidays if provided.
However, because the function includes both the starting and ending dates in its calculation, calculating the difference between two dates might yield a number that is one day too high for standard overdue calculations. Subtracting 1 corrects this behavior.
Ensure your project deadline date is in one cell (for example, A2) and the current status date or today's date is in another cell (for example, B2). Place your list of custom holidays in a separate range, such as D2:D10.
In your designated result cell, begin by typing the formula `=NETWORKDAYS(A2, B2, D2:D10)`. This will calculate the total working days between the two dates, excluding your specified holidays.
Modify the formula to `=NETWORKDAYS(A2, B2, D2:D10) - 1`. This adjustment corrects the inclusive counting behavior, ensuring you get an accurate negative number for days remaining or a positive number for days overdue.
To return a blank cell when the required date conditions are not met (e.g., the cell is empty), wrap your formula in an IF function: `=IF(OR(A2="", B2=""), "", NETWORKDAYS(A2, B2, D2:D10) - 1)`.
Calculate Project Deadlines Easily in WPS Spreadsheet
WPS Spreadsheet provides full support for advanced date and time functions, including NETWORKDAYS, allowing you to accurately track project timelines, deadlines, and working days with ease.
- 1. Open Your Project Tracker: Launch WPS Spreadsheet and open the workbook where you track your deadlines.
- 2. Access Date Functions: Click on the cell where you want the calculation, go to the Formulas tab, select Date & Time, and choose NETWORKDAYS.
- 3. Input the Parameters: Select your start date, end date, and highlight your custom holiday range.
- 4. Apply and Drag: Add '- 1' to the end of the formula in the formula bar, press Enter, and drag the fill handle down to apply it to all your projects.

Frequently Asked Questions
Why does NETWORKDAYS return a number that is one day higher than expected?
NETWORKDAYS calculates the total number of working days inclusive of both the start date and the end date. To get the strict mathematical difference in days between the two dates, you must subtract 1 from the final result.
How do I account for specific company holidays in my calculation?
You can list your specific holiday dates in a separate column or range. Then, add this range as the third, optional argument in the NETWORKDAYS function, formatted as =NETWORKDAYS(start_date, end_date, holiday_range).
How can I calculate working days if my weekend is not Saturday and Sunday?
If your workweek uses different weekend days, use the NETWORKDAYS.INTL function instead. This function allows you to specify exactly which days of the week should be considered non-working weekend days.
How do I make the cell appear blank if the deadline date is missing?
You can wrap your NETWORKDAYS formula in an IF statement to check for blank cells. For example, using =IF(ISBLANK(A2), "", NETWORKDAYS(A2, B2)-1) will leave the cell blank until a date is entered in cell A2.