How to Make Saturday and Sunday Workdays in Project Web App
Question details
The user needs to configure Project Web to recognize weekends as valid working days instead of automatically moving deadlines to weekdays.

- Product
- Project Web App (PWA)
- Device & OS
- not provided
- Scenario
- Scheduling tasks or allocating resource hours that require Saturday and Sunday work.
- Observed behavior
- Project Web automatically moves weekend deadlines to the nearest working day (usually Monday), even after individual resource hours are modified.
Ensure you have administrator permissions in Project Web App (PWA), as creating or editing Enterprise Calendars requires admin rights and affects resource scheduling globally.
Configure and Assign an Enterprise Calendar for Weekend Work
Create or modify a base calendar in PWA settings to explicitly include Saturdays and Sundays as working days, then assign it to the necessary resources.
By default, standard enterprise calendars treat weekends as non-working time. To fix the shifting deadlines, you must update the global Enterprise Calendar and ensure the specific resource is using it as their Base Calendar.
Open Project Web App, click the gear icon in the top right corner to open settings, and select 'PWA Settings'.
Under the 'Enterprise Data' section, locate and click on 'Enterprise Calendars'.
Select an existing calendar and click 'Edit', or click 'New Calendar' to create a custom schedule specifically for weekend workers.
In the calendar configuration window, navigate to the Work Weeks tab, click on Details, select both Saturday and Sunday, and set them to your required working times. Save the calendar.
Go to the Resources page in PWA, select and edit the relevant resource, and change their 'Base Calendar' dropdown to the newly configured calendar. Save your changes.

Manage Project Schedules Flexibly with WPS Office
If configuring enterprise server settings in Project Web App is too rigid or complex, WPS Spreadsheet offers a lightweight and highly customizable alternative for project tracking. You can build versatile Gantt charts and timelines without restrictive calendar rules.
- 1. Open WPS Spreadsheet: Launch WPS Office and click on 'Spreadsheet' to start a new project workbook.
- 2. Find a Project Template: Navigate to the 'Templates' tab and search for 'Project Schedule' or 'Gantt Chart'.
- 3. Customize Your Schedule: Apply the template and freely input weekend dates without automated software restrictions shifting your deadlines.

Frequently Asked Questions
Why do my task dates automatically change to Monday in Project Web?
By default, the standard enterprise calendar in Project Web sets Saturday and Sunday as non-working days. If a task is scheduled to finish on a weekend, the scheduling engine automatically pushes the deadline to the next available working day.
Can I change working days for just one specific project resource?
Yes. You can create a custom base calendar in Enterprise Calendars with weekend workdays enabled, and then assign that specific calendar only to the resources who work on weekends via the Resources page.
Do I need admin rights to change the Enterprise Calendar?
Yes, modifying or creating Enterprise Calendars requires Project Web App administrator permissions. If you do not have these permissions, you will need to contact your organization's PWA administrator to make the changes.