How to Prevent Tasks from Running Simultaneously in Microsoft Project
Question details
The user wants to prevent two tasks from occurring at the same time in Microsoft Project without forcing a rigid predecessor-successor relationship, as the tasks can happen in any order.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Building reusable project templates where certain tasks cannot overlap but do not require a strict execution order, and where fixed dates or forced links would create inaccurate automatic schedule calculations.
- Observed behavior
- Microsoft Project does not offer a direct 'either-or' or 'do not overlap' task constraint natively.
Verify if the tasks truly cannot overlap due to physical constraints, such as sharing the same location, personnel, or equipment, before applying a scheduling workaround.
Use a Shared Resource with Resource Leveling
By creating a dummy shared resource and assigning it to both tasks, you can leverage Microsoft Project's built-in leveling engine to automatically sequence the tasks without overlapping.
This method works best because it avoids hardcoding task dependencies. If a delay occurs in one part of the project, the leveling engine dynamically recalculates the schedule to ensure the shared resource is never over-allocated.
Navigate to the 'View' tab, select 'Resource Sheet', and create a new Work resource named 'Non-concurrent Constraint' with a Max Units setting of 100%.
Switch back to the Gantt Chart view. Double-click the first task, go to the 'Resources' tab, and assign the 'Non-concurrent Constraint' resource. Repeat this step for the second task.
Go to the 'Resource' tab on the top ribbon and click 'Level Resource' or 'Level All'. Project will automatically delay one of the tasks so they run sequentially based on available slack and priority.

Establish a Temporary Task Sequence
Manually set an assumed order for the tasks using standard dependencies, and adjust the schedule during execution if the sequence changes.
Simplify Project Scheduling with WPS Office
If complex software constraints like those in Microsoft Project are slowing you down, consider managing your tasks with WPS Office. With its intuitive interface and versatile spreadsheet capabilities, you can easily track project timelines using highly customizable, free Gantt chart templates.
- 1. Download and install: Get WPS Office for free from the official website and open WPS Spreadsheet.
- 2. Find a project template: Click on 'Templates' from the homepage and search for 'Project Schedule' or 'Gantt Chart'.
- 3. Customize your timeline: Fill in your task details and visually arrange your timeline without fighting strict software constraints.

Frequently Asked Questions
Does Microsoft Project have a native 'do not overlap' task constraint?
No. Microsoft Project requires either a defined predecessor-successor relationship or resource limitations to prevent tasks from overlapping. It lacks a direct 'either-or' constraint for independent tasks.
Why shouldn't I use fixed dates to prevent tasks from running simultaneously?
Using fixed start or finish dates creates rigid constraints in Microsoft Project. If an earlier project phase is delayed, fixed dates will prevent the scheduling engine from dynamically updating the timeline, resulting in an inaccurate schedule.
How does resource leveling resolve simultaneous task conflicts?
When you assign a single unit of a shared resource to two tasks, resource leveling recognizes that the resource cannot be in two places at once. It automatically delays the lower-priority task until the resource is freed, ensuring the tasks execute sequentially.